December 9, 2022
- Traffic signals have been set.
- Prep work has started for ped ramps at Pueblo - waiting on concrete.
- Water work will resume on Hays between 11th and 12th next year.
- Power service is scheduled for December 20th at 11th and Franklin.
Share December 9, 2022 on Facebook
Share December 9, 2022 on X (formerly Twitter)
Share December 9, 2022 on Linkedin
Email December 9, 2022 link
This project is substantially complete.