June 2, 2023

  • IMC started May 8th at 12th and Hays - Electrical work complete.
  • Concrete placements ongoing.
  • Paving 12th and Hays intersection scheduled for the end of the week - June 1st and 2nd.
  • Contractor expects to start on 11th (Fort to Franklin) first week of June.