June 2, 2023
- IMC started May 8th at 12th and Hays - Electrical work complete.
- Concrete placements ongoing.
- Paving 12th and Hays intersection scheduled for the end of the week - June 1st and 2nd.
- Contractor expects to start on 11th (Fort to Franklin) first week of June.