  • Contractor started on 11th - Fort to Franklin first week of June - roadway demo complete.
  • Electrical work ongoing.
  • Concrete sidewalk placements scheduled for the last week of June.
  • Anticipated pave date targeted for the end of July.
Share June 23, 2023 on Facebook Share June 23, 2023 on X (formerly Twitter) Share June 23, 2023 on Linkedin Email June 23, 2023 link

This project is substantially complete. 