- IMC started work May 8th at 12th and Hays - Electrical work ongoing.
- Concrete placement scheduled for May 25th.
- Contractor expects to start on 11th (Fort to Franklin) first week of June.
Share May 26, 2023 on Facebook
Share May 26, 2023 on Twitter
Share May 26, 2023 on Linkedin
Email May 26, 2023 link
This project is substantially complete.