May 26, 2023
- IMC started work May 8th at 12th and Hays - Electrical work ongoing.
- Concrete placement scheduled for May 25th.
- Contractor expects to start on 11th (Fort to Franklin) first week of June.
Share May 26, 2023 on Facebook
Share May 26, 2023 on X (formerly Twitter)
Share May 26, 2023 on Linkedin
Email May 26, 2023 link
This project is substantially complete.