May 26, 2023

  • IMC started work May 8th at 12th and Hays - Electrical work ongoing.
  • Concrete placement scheduled for May 25th.
  • Contractor expects to start on 11th (Fort to Franklin) first week of June.
Share May 26, 2023 on Facebook Share May 26, 2023 on X (formerly Twitter) Share May 26, 2023 on Linkedin Email May 26, 2023 link

This project is substantially complete. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>