November 23, 2022
- Intersection has been reopened to traffic.
- Waiting on signals to be set.
- Prep work has started for ped ramps at Pueblo.
- Water work will resume on Hays between 11th and 12th, once the work on Fort is complete.
Share November 23, 2022 on Facebook
Share November 23, 2022 on Twitter
Share November 23, 2022 on Linkedin
Email November 23, 2022 link
This project is substantially complete.