October 28, 2022

  • The intersection of 11th and Fort is closed for roadwork and pedestrian modifications.
  • Contractor started work on October 3rd at the intersection of Fort and 11th.
  • All four corners are demoed.
  • Concrete form work set in preparation for concrete.
  • Paving mainline from Fort to Resseguie Friday, October 28th.
  • Water work will resume on Hays between 11th and 12th, once the work on Fort is complete.
Share October 28, 2022 on Facebook Share October 28, 2022 on Twitter Share October 28, 2022 on Linkedin Email October 28, 2022 link

This project is substantially complete. 