11th Street Bikeway

Share 11th Street Bikeway on Facebook Share 11th Street Bikeway on Twitter Share 11th Street Bikeway on Linkedin Email 11th Street Bikeway link

This project is substantially complete. 

Review the story map of the 11th Street project here!

The Ada County Highway District (ACHD) started construction mid-April and is anticipated to finish November of 2022.

ACHD is constructing a bikeway that includes a multi-use pathway thru the Boise High School campus, wayfinding and bikeway signage, enhanced crossings, sharrows, and bike lanes. Suez will also be installing a water line down 11th Street between Heron and Fort streets.

What to expect during construction:

  • Lane restrictions
  • Temporary on-street parking impacts
  • Short-term closures
  • Temporary pedestrian detours
  • Equipment back up alarms and ground vibration
  • General construction noise and dust

Contractors will coordinate with property owners to maintain access during construction and crews will work between 7 a.m. to 7 p.m., unless otherwise approved.

Due to contractor staffing issues and supply-chain shortages, construction schedules could change.

Project Description

The Ada County Highway District (ACHD) designed bikeway improvements for 11th Street from Heron to State to create a continuous connection from the North End and Camel's Back Park to Downtown Boise.

Highlights

  • Rehabilitate the pavement on 11th Street between Washington and Heron Streets.
  • Install enhanced pedestrian crossings at Fort/11th, Hays/11th, and Hays/12th with bicycle push buttons and bulb-outs.
  • Construct a new multi-use pathway through the Boise High School campus with all-way stop intersections at Franklin and Washington streets.
  • A phased approach near Washington Street which will start with painted sharrows (a lane marking that indicates vehicles and cyclists share the road). A future phase may add full bicycle lanes which will remove parking along this section (approximately 10 spaces). This will be determined after coordination with the YMCA and City of Boise.
  • Install new pedestrian-scale lighting at the bulb outs and multi-use pathway.

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

Review the story map of the 11th Street project here!

The Ada County Highway District (ACHD) started construction mid-April and is anticipated to finish November of 2022.

ACHD is constructing a bikeway that includes a multi-use pathway thru the Boise High School campus, wayfinding and bikeway signage, enhanced crossings, sharrows, and bike lanes. Suez will also be installing a water line down 11th Street between Heron and Fort streets.

What to expect during construction:

  • Lane restrictions
  • Temporary on-street parking impacts
  • Short-term closures
  • Temporary pedestrian detours
  • Equipment back up alarms and ground vibration
  • General construction noise and dust

Contractors will coordinate with property owners to maintain access during construction and crews will work between 7 a.m. to 7 p.m., unless otherwise approved.

Due to contractor staffing issues and supply-chain shortages, construction schedules could change.

Project Description

The Ada County Highway District (ACHD) designed bikeway improvements for 11th Street from Heron to State to create a continuous connection from the North End and Camel's Back Park to Downtown Boise.

Highlights

  • Rehabilitate the pavement on 11th Street between Washington and Heron Streets.
  • Install enhanced pedestrian crossings at Fort/11th, Hays/11th, and Hays/12th with bicycle push buttons and bulb-outs.
  • Construct a new multi-use pathway through the Boise High School campus with all-way stop intersections at Franklin and Washington streets.
  • A phased approach near Washington Street which will start with painted sharrows (a lane marking that indicates vehicles and cyclists share the road). A future phase may add full bicycle lanes which will remove parking along this section (approximately 10 spaces). This will be determined after coordination with the YMCA and City of Boise.
  • Install new pedestrian-scale lighting at the bulb outs and multi-use pathway.

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

This project is substantially complete. 

  • March 17, 2023

    Share March 17, 2023 on Facebook Share March 17, 2023 on Twitter Share March 17, 2023 on Linkedin Email March 17, 2023 link
    • Water work will resume on Hays between 11th and 12th around the middle of April.
    • Contractor will be back in the summer when school is out to complete the section of work from Fort to Franklin.
  • March 10, 2023

    Share March 10, 2023 on Facebook Share March 10, 2023 on Twitter Share March 10, 2023 on Linkedin Email March 10, 2023 link
    • Water work will resume on Hays between 11th and 12th on March 20th.
    • Contractor will be back in the summer to complete the section of work from Fort to Franklin - when school is out of session.
  • March 3, 2023

    Share March 3, 2023 on Facebook Share March 3, 2023 on Twitter Share March 3, 2023 on Linkedin Email March 3, 2023 link
    • Water work will resume on Hays between 11th and 12th on March 20th.
    • Contractor will be back in the summer to complete the section of work from Fort to Franklin - when school is out of session.
  • February 24, 2023

    Share February 24, 2023 on Facebook Share February 24, 2023 on Twitter Share February 24, 2023 on Linkedin Email February 24, 2023 link
    • Water work will resume on Hays between 11th and 12th on March 20th.
    • Contractor will be back in the summer (when school is out) to complete the section of work from Fort to Franklin.
  • February 17, 2023

    Share February 17, 2023 on Facebook Share February 17, 2023 on Twitter Share February 17, 2023 on Linkedin Email February 17, 2023 link
    • Water work will resume on Hays between 11th and 12th on March 20th.
    • Contractor will be back in the summer to complete the section of work from Fort to Franklin - when school is out of session.
  • February 10, 2023

    Share February 10, 2023 on Facebook Share February 10, 2023 on Twitter Share February 10, 2023 on Linkedin Email February 10, 2023 link
    • Water work will resume on Hays between 11th and 12th on March 20th.
    • Contractor will be back in the summer (when school is out) to complete the work from Fort to Franklin.
  • February 3, 2023

    Share February 3, 2023 on Facebook Share February 3, 2023 on Twitter Share February 3, 2023 on Linkedin Email February 3, 2023 link
    • Water work will resume on Hays between 11th and 12th on March 20th.
    • Contractor will be back in the summer to complete the section of work from Fort to Franklin (when school is out for summer).
  • January 27, 2023

    Share January 27, 2023 on Facebook Share January 27, 2023 on Twitter Share January 27, 2023 on Linkedin Email January 27, 2023 link
    • Water work will resume on Hays between 11th and 12th early this year.
    • Contractor will be back in the summer when school is out to complete the section of work from Fort to Franklin.
  • January 20, 2023

    Share January 20, 2023 on Facebook Share January 20, 2023 on Twitter Share January 20, 2023 on Linkedin Email January 20, 2023 link
    • Concrete at Pueblo complete.
    • Water work will resume on Hays between 11th and 12th early this year.
    • Power service is complete.
    • Contractor will be back in the summer (when school is out) to complete the section of work from Fort to Franklin.
  • January 13, 2023

    Share January 13, 2023 on Facebook Share January 13, 2023 on Twitter Share January 13, 2023 on Linkedin Email January 13, 2023 link
    • Concrete at Pueblo complete.
    • Water work will resume on Hays between 11th and 12th early this year.
    • Power service is complete.