December 16, 2022
- 2nd Street, Idaho Avenue to Carlton Avenue - Grade work complete. Concrete work nearly complete. Irrigation work complete. Paving tentatively scheduled for the week of December 12th pending weather. Contractor expects to pave bottom lift December 16th and possibly top lift December 17th.
- 4th Street, Broadway Avenue to State Avenue
- 4th Street, Washington Avenue to North End - Central Paving will patch the trench for Idaho Power on the next pave date.
- 5th Avenue, State Avenue to North End - Substantially complete.
- 5th Avenue, Franklin Road to Bower Street - Substantially complete. Waiting on landscaping.
- Bower Street, 2nd Street to East End - Substantially complete.
- State Avenue, 2nd Street to Cathy Lane - Grade work nearly complete. Concrete prep and curb ongoing. Paving complete at the intersection of 2nd for the parade. Remaining paving is tentatively scheduled for the week of December 12th - pending weather.
- Washington Avenue, 4th Street to Cathy Lane - Substantially complete.
Share December 16, 2022 on Facebook
Share December 16, 2022 on Twitter
Share December 16, 2022 on Linkedin
Email December 16, 2022 link