December 22, 2022

  • 2nd Street, Idaho Avenue to Carlton Avenue - Concrete work nearly complete. Mainline paving complete.
  • 4th Street, Broadway Avenue to State Avenue
  • 4th Street, Washington Avenue to North End - Central Paving patched the trench for Idaho Power.
  • 5th Avenue, State Avenue to North End - Substantially complete.
  • 5th Avenue, Franklin Road to Bower Street - Substantially complete. Waiting on landscaping.
  • Bower Street, 2nd Street to East End - Substantially complete.
  • State Avenue, 2nd Street to Cathy Lane - Substantially complete.
  • Washington Avenue, 4th Street to Cathy Lane - Substantially complete.
Share December 22, 2022 on Facebook Share December 22, 2022 on Twitter Share December 22, 2022 on Linkedin Email December 22, 2022 link

This project is substantially complete.