- 2nd Street, Idaho Avenue to Carlton Avenue - Grade work complete. Concrete work nearly complete. Irrigation work complete. Paving tentatively scheduled for the week of December 12th pending weather.
- 4th Street, Broadway Avenue to State Avenue
- 4th Street, Washington Avenue to North End - Central Paving will patch the trench for Idaho Power on the next pave date.
- 5th Avenue, State Avenue to North End - Substantially complete.
- 5th Avenue, Franklin Road to Bower Street - Substantially complete. Waiting on landscaping.
- Bower Street, 2nd Street to East End - Substantially complete. Minor concrete items remain. Waiting on landscaping.
- State Avenue, 2nd Street to Cathy Lane - Grade work nearly complete. Concrete prep and curb ongoing. Paving complete at the intersection of 2nd for the parade. Remaining paving is tentatively scheduled for the week of December 12th - pending weather.
- Washington Avenue, 4th Street to Cathy Lane - Substantially complete.