November 18, 2022

  • 2nd Street, Idaho Avenue to Carlton Avenue - Grade work ongoing - irrigation work ongoing.
  • 4th Street, Broadway Avenue to State Avenue
  • 4th Street, Washington Avenue to North End - Landscapers on site intermittently - substantially complete.
  • 5th Avenue, State Avenue to North End - Substantially complete.
  • 5th Avenue, Franklin Road to Bower Street - Substantially complete. Waiting on landscaping.
  • Bower Street, 2nd Street to East End - Substantially complete. Minor concrete items remain. Waiting on landscaping.
  • State Avenue, 2nd Street to Cathy Lane - Irrigation work ongoing. Grade work ongoing. Concrete prep and curb started.
  • Washington Avenue, 4th Street to Cathy Lane - Paving complete. Minor house keeping items remain.
Share November 18, 2022 on Facebook Share November 18, 2022 on Twitter Share November 18, 2022 on Linkedin Email November 18, 2022 link

This project is substantially complete.