September 30, 2022

  • E. Washington Avenue, E. 4th Street to N. Cathy Ave - Road is closed. Grade work ongoing. Concrete work is expected to be complete next week.
  • 4th St. - Washington to Janie - Landscapers on site intermittently. Substantially complete.
  • E. 2nd Street, E. Idaho Ave to E. Carlton Ave - Work from Pine to Carlton ongoing.
  • E.5th Ave, E. Franklin Road to E. Bower Street - Minor concrete items remain, driveway approaches remain - waiting on landscaping.
  • E. Bower Street, N. Main Street to east end - Minor concrete items remain. Waiting on landscaping.
  • E. 5th Street, State Ave to the north end - Work substantially complete
Share September 30, 2022 on Facebook Share September 30, 2022 on X (formerly Twitter) Share September 30, 2022 on Linkedin Email September 30, 2022 link

This project is substantially complete.