March 6, 2023 Update

One to two weeks prior to work starting, neighbors will be notified by door knockers indicating that construction will be starting soon. There will also be a message board placed at the entrance of the neighborhood one week before the work is scheduled to begin. Once construction begins, the work on the cul-de-sac will be completed within approximately one week’s time. Access to driveways in the cul-de-sac may be restricted for a portion of the project duration and on-street parking in the project area will be limited during the span of the construction work.

Construction Impacts:

  • General construction noise, dust, equipment backup alarms, and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved


Share March 6, 2023 Update on Facebook Share March 6, 2023 Update on X (formerly Twitter) Share March 6, 2023 Update on Linkedin Email March 6, 2023 Update link

This project is substantially complete.

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>