August 2, 2024
- Project includes work on the following segments:
- Swan Falls Rd, King Rd to Sunbeam St - Complete.
- Stagecoach Way, Swan Falls Rd to Luker Rd - Complete.
- Luker Rd, King Rd to Stagecoach Way - Paving Complete. Minor sidewalk placements remain. Lane lines are scheduled for next week.
- Poen Rd, Swan Falls Rd to Cloverdale Rd - Complete.
Share August 2, 2024 on Facebook
Share August 2, 2024 on Twitter
Share August 2, 2024 on Linkedin
Email August 2, 2024 link
This project is substantially complete.