- Swan Falls Rd, King Rd to Sunbeam St - Complete.
- Stagecoach Way, Swan Falls Rd to Luker Rd - Complete.
- Luker Rd, King Rd to Stagecoach Way - Milling and demo complete.
- Water line work for City of Kuna complete.
- Concrete prep started and placements are scheduled for this week and next. Paving is tentatively scheduled for July 25th – 26th.
- Poen Rd, Swan Falls Rd to Cloverdale Rd - Complete – waiting 45 days before second coat of paint is applied. This is applicable at all locations.