June 14, 2024

Project includes work on the following segments:

  • Swan Falls Rd, King Rd to Sunbeam St
    • Complete.
  • Stagecoach Way, Swan Falls Rd to Luker Rd
    • Paved this week.
    • Shouldering started.
  • Luker Rd, King Rd to Stagecoach Way
    • Irrigation pipe crossing complete and patched back.
    • Remaining work expected to start next week.
  • Poen Rd, Swan Falls Rd to Cloverdale Rd
    • Complete – waiting 45 days before second coat of paint is applied. This is applicable at all locations.
Share June 14, 2024 on Facebook Share June 14, 2024 on X (formerly Twitter) Share June 14, 2024 on Linkedin Email June 14, 2024 link

This project is substantially complete. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>