June 14, 2024
Project includes work on the following segments:
- Swan Falls Rd, King Rd to Sunbeam St
- Complete.
- Stagecoach Way, Swan Falls Rd to Luker Rd
- Paved this week.
- Shouldering started.
- Luker Rd, King Rd to Stagecoach Way
- Irrigation pipe crossing complete and patched back.
- Remaining work expected to start next week.
- Poen Rd, Swan Falls Rd to Cloverdale Rd
- Complete – waiting 45 days before second coat of paint is applied. This is applicable at all locations.
Share June 14, 2024 on Facebook
Share June 14, 2024 on Twitter
Share June 14, 2024 on Linkedin
Email June 14, 2024 link
This project is substantially complete.