June 28, 2024

  • Swan Falls Rd, King Rd to Sunbeam St - Complete.
  • Stagecoach Way, Swan Falls Rd to Luker Rd - Paved this week. Shouldering started.
  • Luker Rd, King Rd to Stagecoach Way - Milling and demo started. Water line work for City of Kuna starting Friday.
  • Poen Rd, Swan Falls Rd to Cloverdale Rd - Complete – waiting 45 days before second coat of paint is applied. This is applicable at all locations.
Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link

This project is substantially complete. 