June 7, 2024

Project includes work on the following segments:

  • Swan Falls Rd, King Rd to Sunbeam St
    • Paving complete.
    • Shouldering complete as of May 28th
  • Stagecoach Way, Swan Falls Rd to Luker Rd
    • Closure started May 30th
    • Milling complete.
  • Luker Rd, King Rd to Stagecoach Way
    • Irrigation pipe crossing complete and patched back.
    • Remaining work expected to start next week
  • Poen Rd, Swan Falls Rd to Cloverdale Rd
    • Complete – waiting 45 days before second coat of paint is applied.
Share June 7, 2024 on Facebook Share June 7, 2024 on X (formerly Twitter) Share June 7, 2024 on Linkedin Email June 7, 2024 link

This project is substantially complete. 