Project includes work on the following segments:
- Swan Falls Rd, King Rd to Sunbeam St
- Paving complete.
- Shouldering complete as of May 28th
- Stagecoach Way, Swan Falls Rd to Luker Rd
- Closure started May 30th
- Milling complete.
- Luker Rd, King Rd to Stagecoach Way
- Irrigation pipe crossing complete and patched back.
- Remaining work expected to start next week
- Poen Rd, Swan Falls Rd to Cloverdale Rd
- Complete – waiting 45 days before second coat of paint is applied.
Share June 7, 2024 on Facebook
Share June 7, 2024 on X (formerly Twitter)
Share June 7, 2024 on Linkedin
Email June 7, 2024 link
This project is substantially complete.