- Swan Falls Rd, King Rd to Sunbeam St - Contractor started milling this week.
- Stagecoach Way, Swan Falls Rd to Luker Rd
- Luker Rd, King Rd to Stagecoach Way - Irrigation pipe crossing complete and patched back. Remaining work waiting until Swan Falls is done.
- Poen Rd, Swan Falls Rd to Cloverdale Rd - Lane lines are scheduled to be painted this week, if crews are available.
Share May 16, 2024 on Facebook
Share May 16, 2024 on X (formerly Twitter)
Share May 16, 2024 on Linkedin
Email May 16, 2024 link
This project is substantially complete.