May 31, 2024

  • Swan Falls Rd, King Rd to Sunbeam St - Paving complete. Shouldering complete as of May 28th.
  • Stagecoach Way, Swan Falls Rd to Luker Rd - Closure expected to start May 30th.
  • Luker Rd, King Rd to Stagecoach Way - Irrigation pipe crossing complete and patched back. Remaining work expected to start next week.
  • Poen Rd, Swan Falls Rd to Cloverdale Rd - Lane lines are scheduled to be painted next week, if crews are available.
Share May 31, 2024 on Facebook Share May 31, 2024 on X (formerly Twitter) Share May 31, 2024 on Linkedin Email May 31, 2024 link

This project is substantially complete. 