In January 2024, The Ada County Highway District (ACHD) will start construction on the 2024 Arterial and Collector Capital Maintenance Project. This maintenance project includes pavement rehabilitation, upgraded pedestrian ramps, and new curb, gutter, and sidewalk at certain locations. Construction is anticipated to be completed late in the summer of 2024.

Road Segments

  • Swan Falls Road, King Road to Sunbeam Street
  • Stagecoach Way, Swan Falls Road to Luker Road
  • Luker Road, King Road to Stagecoach Way
    • Fill in a sidewalk gap on Luker Road between Access Street and Stage Coach Way
    • Replace an existing culvert at the Luker Road and Stagecoach Road intersection
  • Poen Road, Swan Falls Road to Cloverdale Road

Construction Impacts

  • Temporary road closures and lane restrictions
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 6 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize construction impacts

In January 2024, The Ada County Highway District (ACHD) will start construction on the 2024 Arterial and Collector Capital Maintenance Project. This maintenance project includes pavement rehabilitation, upgraded pedestrian ramps, and new curb, gutter, and sidewalk at certain locations. Construction is anticipated to be completed late in the summer of 2024.

Road Segments

  • Swan Falls Road, King Road to Sunbeam Street
  • Stagecoach Way, Swan Falls Road to Luker Road
  • Luker Road, King Road to Stagecoach Way
    • Fill in a sidewalk gap on Luker Road between Access Street and Stage Coach Way
    • Replace an existing culvert at the Luker Road and Stagecoach Road intersection
  • Poen Road, Swan Falls Road to Cloverdale Road

Construction Impacts

  • Temporary road closures and lane restrictions
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 6 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize construction impacts

This project is substantially complete. 

  • March 29, 2024

    Share March 29, 2024 on Facebook Share March 29, 2024 on Twitter Share March 29, 2024 on Linkedin Email March 29, 2024 link
    • Luker Rd, King Rd to Stagecoach Way - Irrigation pipe crossing complete and patched back.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd.
      • Phase 1 Shoulder work continues.
      • Paving is complete on the south side of the road.
      • Contractor has started on north side of the road, milling and excavating.
  • March 21, 2024

    Share March 21, 2024 on Facebook Share March 21, 2024 on Twitter Share March 21, 2024 on Linkedin Email March 21, 2024 link
    • Luker Rd, King Rd to Stagecoach Way - Irrigation pipe crossing complete.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Phase 1 Shoulder work. Paving is scheduled for this week for south side. Contractor expects to start on north side next week.
  • March 15, 2024

    Share March 15, 2024 on Facebook Share March 15, 2024 on Twitter Share March 15, 2024 on Linkedin Email March 15, 2024 link
    • Luker Rd, King Rd to Stagecoach Way - Started irrigation pipe crossing.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Phase 1 Shoulder work. Continue excavating on the south side of the road. Contractor expects to start on north side next week.
  • March 8, 2024

    Share March 8, 2024 on Facebook Share March 8, 2024 on Twitter Share March 8, 2024 on Linkedin Email March 8, 2024 link
    • Luker Rd, King Rd to Stagecoach Way - Started irrigation pipe crossing.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Phase 1 Shoulder work. Continue excavating on the south side of the road.
  • March 1, 2024

    Share March 1, 2024 on Facebook Share March 1, 2024 on Twitter Share March 1, 2024 on Linkedin Email March 1, 2024 link
    • King Rd to Stagecoach Way - Started potholing utilities in preparation for pipe replacement at irrigation ditch.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Phase 1 Shoulder work. Started milling and excavating.
  • January 12, 2024

    Share January 12, 2024 on Facebook Share January 12, 2024 on Twitter Share January 12, 2024 on Linkedin Email January 12, 2024 link
    • Notice to proceed is scheduled for January.
    • Contractor plans to start on Poen Road shoulder wok the first part of February, weather dependent.
    • Project includes work on the following segments: Swan Falls Rd, King Rd to Sunbeam St - Stagecoach Way, Swan Falls Rd to Luker Rd - Luker Rd, King Rd to Stagecoach Way - Poen Rd, Swan Falls Rd to Cloverdale Rd – Phase 1 shoulder work.
  • December 22, 2023

    Share December 22, 2023 on Facebook Share December 22, 2023 on Twitter Share December 22, 2023 on Linkedin Email December 22, 2023 link

    Pre-Construction Meeting TBD

    Notice to Proceed is scheduled for January.