September 13, 2024
- Floating Feather Bridge #2024 - Epoxy overlay is complete. Remaining work includes permanent pavement markings.
- N Bridge Ave Bridge #2080 - Epoxy overlay is complete. Remaining work includes permanent pavement markings.
- Knapp Ave Bridge #2097 - Epoxy overlay is complete. Remaining work includes permanent pavement markings.
- Kuna Rd Bridge #2135 - Epoxy overlay is complete. Remaining work includes permanent pavement markings.
- Findley Ave Bridge #2159 - Epoxy overlay is complete. Remaining work includes permanent pavement markings.
- Wright Street Bridge #2170 - Epoxy overlay is nearly complete.
Share September 13, 2024 on Facebook
Share September 13, 2024 on Twitter
Share September 13, 2024 on Linkedin
Email September 13, 2024 link
This project is substantially complete.