September 13, 2024

  • Floating Feather Bridge #2024 - Epoxy overlay is complete. Remaining work includes permanent pavement markings.
  • N Bridge Ave Bridge #2080 - Epoxy overlay is complete. Remaining work includes permanent pavement markings.
  • Knapp Ave Bridge #2097 - Epoxy overlay is complete. Remaining work includes permanent pavement markings.
  • Kuna Rd Bridge #2135 - Epoxy overlay is complete. Remaining work includes permanent pavement markings.
  • Findley Ave Bridge #2159 - Epoxy overlay is complete. Remaining work includes permanent pavement markings.
  • Wright Street Bridge #2170 - Epoxy overlay is nearly complete.
Share September 13, 2024 on Facebook Share September 13, 2024 on X (formerly Twitter) Share September 13, 2024 on Linkedin Email September 13, 2024 link

This project is substantially complete. 