2024 Cul-de-Sac Repair

Share 2024 Cul-de-Sac Repair on Facebook Share 2024 Cul-de-Sac Repair on Twitter Share 2024 Cul-de-Sac Repair on Linkedin Email 2024 Cul-de-Sac Repair link

This project is substantially complete. 

As part of the Ada County Highway District’s (ACHD) Cul-de-Sac Maintenance Program, ACHD will reconstruct and repave several culs-de-sac in Boise, as early as the beginning of May 2024 or possibly as late as mid-September 2024.

One week prior to work starting, message boards will be placed at the entrance of your neighborhood. Once construction begins, the work on your cul-de-sac will be completed within approximately two week’s time.*

Culs-de-Sac included in the work:

  • Avery Place, Wagonmaster Place, and Laramie Place in Southeast Boise
  • Coral Street, south of Rose Hill Street
  • Kerr Place, north of Malad Street
  • Priest Place, east of Division Avenue
  • Falling Brook Way, east of Gekeler Lane

Construction impacts:

  • Access to driveways in the cul-de-sac may be restricted for a portion of the project duration and on-street parking in the project area will be limited during the span of the construction work
  • General construction noise, dust, equipment backup alarms, and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved

As part of the Ada County Highway District’s (ACHD) Cul-de-Sac Maintenance Program, ACHD will reconstruct and repave several culs-de-sac in Boise, as early as the beginning of May 2024 or possibly as late as mid-September 2024.

One week prior to work starting, message boards will be placed at the entrance of your neighborhood. Once construction begins, the work on your cul-de-sac will be completed within approximately two week’s time.*

Culs-de-Sac included in the work:

  • Avery Place, Wagonmaster Place, and Laramie Place in Southeast Boise
  • Coral Street, south of Rose Hill Street
  • Kerr Place, north of Malad Street
  • Priest Place, east of Division Avenue
  • Falling Brook Way, east of Gekeler Lane

Construction impacts:

  • Access to driveways in the cul-de-sac may be restricted for a portion of the project duration and on-street parking in the project area will be limited during the span of the construction work
  • General construction noise, dust, equipment backup alarms, and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved

This project is substantially complete. 

  • September 6, 2024

    Share September 6, 2024 on Facebook Share September 6, 2024 on Twitter Share September 6, 2024 on Linkedin Email September 6, 2024 link
    • Eastgate: Complete.
    • S Avery Place: Complete.
    • S Laramie Place: Complete.
    • Wagonmaster Place: Contractor has removed existing asphalt. Prepping base.
    • Coral Place: Complete.
    • Kerr Place: NA.
    • Falling Brook Way: Complete.
    • S Priest Place: Complete. Contactor needs to fix broken mailboxes.
  • August 30, 2024

    Share August 30, 2024 on Facebook Share August 30, 2024 on Twitter Share August 30, 2024 on Linkedin Email August 30, 2024 link
    • Eastgate: Complete
    • S Avery Place: Complete
    • S Laramie Place: Complete
    • Wagonmaster Place: Contractor has removed existing asphalt. Prepping base.
    • Coral Place: NA
    • Kerr Place: NA
    • Falling Brook Way: NA
    • S Priest Place: Contractor has removed existing asphalt. Prepping base.
  • August 9, 2024

    Share August 9, 2024 on Facebook Share August 9, 2024 on Twitter Share August 9, 2024 on Linkedin Email August 9, 2024 link
    • Eastgate: Contractor started demo of the asphalt on August 7th.
  • June 14, 2024

    Share June 14, 2024 on Facebook Share June 14, 2024 on Twitter Share June 14, 2024 on Linkedin Email June 14, 2024 link
    • Preconstruction meeting is scheduled for June 18th.
    • Notice to proceed is anticipated for July 2024.