2024 Microseal

Share 2024 Microseal on Facebook Share 2024 Microseal on X (formerly Twitter) Share 2024 Microseal on Linkedin Email 2024 Microseal link

This project is substantially complete.

Beginning as early as May*, crews will be working overnight to apply a microseal overlay on various streets in Downtown Meridian and Boise. The microseal process involves cleaning the existing asphalt and then applying a fast-drying asphalt-based sealant. Roadways are microsealed to protect them from water and weather damage, so they stay in good condition.

This project also includes installing a two-stage rectangular rapid flashing beacon (RRFB) across Meridian Road and Main Street at Bower Street.

What to Expect During Microseal:

  • All microseal work will occur at night (8 p.m. to 5 a.m.)
  • Through traffic and on-street parking will be restricted at night while crews are microsealing each road
  • Access will be maintained for businesses, hotels, and residents
  • Flaggers and signage will direct traffic in the areas where crews are applying the microseal and at adjacent intersections
  • Temporary closures

*Due to contractor staffing issues and supply chain shortages, construction schedules could change.

Beginning as early as May*, crews will be working overnight to apply a microseal overlay on various streets in Downtown Meridian and Boise. The microseal process involves cleaning the existing asphalt and then applying a fast-drying asphalt-based sealant. Roadways are microsealed to protect them from water and weather damage, so they stay in good condition.

This project also includes installing a two-stage rectangular rapid flashing beacon (RRFB) across Meridian Road and Main Street at Bower Street.

What to Expect During Microseal:

  • All microseal work will occur at night (8 p.m. to 5 a.m.)
  • Through traffic and on-street parking will be restricted at night while crews are microsealing each road
  • Access will be maintained for businesses, hotels, and residents
  • Flaggers and signage will direct traffic in the areas where crews are applying the microseal and at adjacent intersections
  • Temporary closures

*Due to contractor staffing issues and supply chain shortages, construction schedules could change.

This project is substantially complete.

  • September 26, 2024

    Share September 26, 2024 on Facebook Share September 26, 2024 on X (formerly Twitter) Share September 26, 2024 on Linkedin Email September 26, 2024 link

    Micro seal in Meridian

    • Pavement markings ongoing.
    • Pending weather anticipated complete September 27th.

    Micro seal in Meridian

    • Pavement markings ongoing.
    • Pending weather anticipated complete September 27th.

    This project is substantially complete.

  • September 20, 2024

    Share September 20, 2024 on Facebook Share September 20, 2024 on X (formerly Twitter) Share September 20, 2024 on Linkedin Email September 20, 2024 link
    • Pavement markings ongoing.
    • Pavement markings ongoing.

    This project is substantially complete.

  • September 13, 2024

    Share September 13, 2024 on Facebook Share September 13, 2024 on X (formerly Twitter) Share September 13, 2024 on Linkedin Email September 13, 2024 link
    • Micro seal in Meridian - Pavement markings ongoing.
    • Bower RRFB - Operational.
    • Vista Avenue - Complete.
    • Federal Way - Complete.
    • Micro seal in Meridian - Pavement markings ongoing.
    • Bower RRFB - Operational.
    • Vista Avenue - Complete.
    • Federal Way - Complete.

    This project is substantially complete.

  • September 6, 2024

    Share September 6, 2024 on Facebook Share September 6, 2024 on X (formerly Twitter) Share September 6, 2024 on Linkedin Email September 6, 2024 link

    Micro seal in Meridian

    • Microseal is complete.
    • Pavement markings ongoing.

    Bower RRFB

    • Signal will be activated once pavement markings are complete.

    Vista Avenue

    • Microseal is complete.
    • Pavement markings ongoing.

    Federal Way

    • Micro seal is complete.
    • Pavement markings ongoing.

    Micro seal in Meridian

    • Microseal is complete.
    • Pavement markings ongoing.

    Bower RRFB

    • Signal will be activated once pavement markings are complete.

    Vista Avenue

    • Microseal is complete.
    • Pavement markings ongoing.

    Federal Way

    • Micro seal is complete.
    • Pavement markings ongoing.

    This project is substantially complete.

  • August 30, 2024

    Share August 30, 2024 on Facebook Share August 30, 2024 on X (formerly Twitter) Share August 30, 2024 on Linkedin Email August 30, 2024 link
    • Micro seal in Meridian - Microseal is complete. Pavement markings ongoing.
    • Bower RRFB - Setting poles. Signal activation anticipated by Aug 30th.
    • Vista Avenue - Microseal is complete. Pavement markings ongoing.
    • Federal Way - Micro seal is complete. Pavement markings ongoing.
    • Micro seal in Meridian - Microseal is complete. Pavement markings ongoing.
    • Bower RRFB - Setting poles. Signal activation anticipated by Aug 30th.
    • Vista Avenue - Microseal is complete. Pavement markings ongoing.
    • Federal Way - Micro seal is complete. Pavement markings ongoing.

    This project is substantially complete.

  • August 23, 2024

    Share August 23, 2024 on Facebook Share August 23, 2024 on X (formerly Twitter) Share August 23, 2024 on Linkedin Email August 23, 2024 link

    Micro seal in Meridian - Microseal is complete. Pavement markings ongoing.

    Bower RRFB - Setting poles. Signal activation anticipated by Aug 30th.

    Vista Avenue - Pavement marking removal Aug 18th. Micro seal started Aug 20th.

    Federal Way - Pavement marking removal Aug 19th. Micro seal started Aug 20th.

    Micro seal in Meridian - Microseal is complete. Pavement markings ongoing.

    Bower RRFB - Setting poles. Signal activation anticipated by Aug 30th.

    Vista Avenue - Pavement marking removal Aug 18th. Micro seal started Aug 20th.

    Federal Way - Pavement marking removal Aug 19th. Micro seal started Aug 20th.

    This project is substantially complete.

  • August 15, 2024

    Share August 15, 2024 on Facebook Share August 15, 2024 on X (formerly Twitter) Share August 15, 2024 on Linkedin Email August 15, 2024 link
    • Vista Avenue - Pavement marking removal Aug 18th. Micro seal stating as early as Aug 20th.
    • Federal Way - Pavement marking removal Aug 19th. Micro seal starting as early as Aug 22nd.
    • Vista Avenue - Pavement marking removal Aug 18th. Micro seal stating as early as Aug 20th.
    • Federal Way - Pavement marking removal Aug 19th. Micro seal starting as early as Aug 22nd.

    This project is substantially complete.

  • August 9, 2024

    Share August 9, 2024 on Facebook Share August 9, 2024 on X (formerly Twitter) Share August 9, 2024 on Linkedin Email August 9, 2024 link
    • Crack seal in Meridian complete.
    • RRFB at Meridian Rd & Bower ongoing.
    • Removal of thermoplastic marking started July 22nd and on-going.
    • Microseal in Meridian started August 7th. Work is being done at night.
    • Crack seal in Meridian complete.
    • RRFB at Meridian Rd & Bower ongoing.
    • Removal of thermoplastic marking started July 22nd and on-going.
    • Microseal in Meridian started August 7th. Work is being done at night.

    This project is substantially complete.

  • August 2, 2024

    Share August 2, 2024 on Facebook Share August 2, 2024 on X (formerly Twitter) Share August 2, 2024 on Linkedin Email August 2, 2024 link
    • Contractor anticipates starting Microseal work in August 2024.
    • Crack seal in Meridian complete.
    • RRFB at Meridian Rd & Bower ongoing.
    • Removal of thermoplastic marking starting July 22nd and on-going.
    • Microseal in Meridian anticipated starting August 5th.
    • Contractor anticipates starting Microseal work in August 2024.
    • Crack seal in Meridian complete.
    • RRFB at Meridian Rd & Bower ongoing.
    • Removal of thermoplastic marking starting July 22nd and on-going.
    • Microseal in Meridian anticipated starting August 5th.

    This project is substantially complete.

  • July 26, 2024

    Share July 26, 2024 on Facebook Share July 26, 2024 on X (formerly Twitter) Share July 26, 2024 on Linkedin Email July 26, 2024 link
    • Contractor anticipates starting Microseal work in August 2024.
    • Crack seal in Meridian complete.
    • RRFB at Meridian Rd & Bower ongoing.
    • Removal of thermoplastic marking starting July 22nd and on-going.
    • Contractor anticipates starting Microseal work in August 2024.
    • Crack seal in Meridian complete.
    • RRFB at Meridian Rd & Bower ongoing.
    • Removal of thermoplastic marking starting July 22nd and on-going.

    This project is substantially complete.