Micro seal in Meridian
- Pavement markings ongoing.
- Pending weather anticipated complete September 27th.
Share September 20, 2024 on Facebook
Share September 20, 2024 on Linkedin
Email September 20, 2024 link
- Pavement markings ongoing.
Share September 13, 2024 on Facebook
Share September 13, 2024 on Linkedin
Email September 13, 2024 link
- Micro seal in Meridian - Pavement markings ongoing.
- Bower RRFB - Operational.
- Vista Avenue - Complete.
- Federal Way - Complete.
Share September 6, 2024 on Facebook
Share September 6, 2024 on Linkedin
Email September 6, 2024 link
Micro seal in Meridian
- Microseal is complete.
- Pavement markings ongoing.
Bower RRFB
- Signal will be activated once pavement markings are complete.
Vista Avenue
- Microseal is complete.
- Pavement markings ongoing.
Federal Way
- Micro seal is complete.
- Pavement markings ongoing.
Share August 30, 2024 on Facebook
Share August 30, 2024 on Linkedin
Email August 30, 2024 link
- Micro seal in Meridian - Microseal is complete. Pavement markings ongoing.
- Bower RRFB - Setting poles. Signal activation anticipated by Aug 30th.
- Vista Avenue - Microseal is complete. Pavement markings ongoing.
- Federal Way - Micro seal is complete. Pavement markings ongoing.
Share August 23, 2024 on Facebook
Share August 23, 2024 on Linkedin
Email August 23, 2024 link
Micro seal in Meridian - Microseal is complete. Pavement markings ongoing.
Bower RRFB - Setting poles. Signal activation anticipated by Aug 30th.
Vista Avenue - Pavement marking removal Aug 18th. Micro seal started Aug 20th.
Federal Way - Pavement marking removal Aug 19th. Micro seal started Aug 20th.
Share August 15, 2024 on Facebook
Share August 15, 2024 on Linkedin
Email August 15, 2024 link
- Vista Avenue - Pavement marking removal Aug 18th. Micro seal stating as early as Aug 20th.
- Federal Way - Pavement marking removal Aug 19th. Micro seal starting as early as Aug 22nd.
Share August 9, 2024 on Facebook
Share August 9, 2024 on Linkedin
Email August 9, 2024 link
- Crack seal in Meridian complete.
- RRFB at Meridian Rd & Bower ongoing.
- Removal of thermoplastic marking started July 22nd and on-going.
- Microseal in Meridian started August 7th. Work is being done at night.
Share August 2, 2024 on Facebook
Share August 2, 2024 on Linkedin
Email August 2, 2024 link
- Contractor anticipates starting Microseal work in August 2024.
- Crack seal in Meridian complete.
- RRFB at Meridian Rd & Bower ongoing.
- Removal of thermoplastic marking starting July 22nd and on-going.
- Microseal in Meridian anticipated starting August 5th.
Share July 26, 2024 on Facebook
Share July 26, 2024 on Linkedin
Email July 26, 2024 link
- Contractor anticipates starting Microseal work in August 2024.
- Crack seal in Meridian complete.
- RRFB at Meridian Rd & Bower ongoing.
- Removal of thermoplastic marking starting July 22nd and on-going.