This project is substantially complete.

Beginning as early as May*, crews will be working overnight to apply a microseal overlay on various streets in Downtown Meridian and Boise. The microseal process involves cleaning the existing asphalt and then applying a fast-drying asphalt-based sealant. Roadways are microsealed to protect them from water and weather damage, so they stay in good condition.

This project also includes installing a two-stage rectangular rapid flashing beacon (RRFB) across Meridian Road and Main Street at Bower Street.

What to Expect During Microseal:

  • All microseal work will occur at night (8 p.m. to 5 a.m.)
  • Through traffic and on-street parking will be restricted at night while crews are microsealing each road
  • Access will be maintained for businesses, hotels, and residents
  • Flaggers and signage will direct traffic in the areas where crews are applying the microseal and at adjacent intersections
  • Temporary closures

*Due to contractor staffing issues and supply chain shortages, construction schedules could change.

Beginning as early as May*, crews will be working overnight to apply a microseal overlay on various streets in Downtown Meridian and Boise. The microseal process involves cleaning the existing asphalt and then applying a fast-drying asphalt-based sealant. Roadways are microsealed to protect them from water and weather damage, so they stay in good condition.

This project also includes installing a two-stage rectangular rapid flashing beacon (RRFB) across Meridian Road and Main Street at Bower Street.

What to Expect During Microseal:

  • All microseal work will occur at night (8 p.m. to 5 a.m.)
  • Through traffic and on-street parking will be restricted at night while crews are microsealing each road
  • Access will be maintained for businesses, hotels, and residents
  • Flaggers and signage will direct traffic in the areas where crews are applying the microseal and at adjacent intersections
  • Temporary closures

*Due to contractor staffing issues and supply chain shortages, construction schedules could change.

This project is substantially complete.

  • July 19, 2024

    Share July 19, 2024 on Facebook Share July 19, 2024 on X (formerly Twitter) Share July 19, 2024 on Linkedin Email July 19, 2024 link
    • Contractor anticipates starting Microseal work in August 2024.
    • Crack seal in Meridian complete.
    • RRFB at Meridian Rd & Bower ongoing.
    • Removal of thermoplastic marking starting July 22nd.
    • Contractor anticipates starting Microseal work in August 2024.
    • Crack seal in Meridian complete.
    • RRFB at Meridian Rd & Bower ongoing.
    • Removal of thermoplastic marking starting July 22nd.

    This project is substantially complete.

  • July 12, 2024

    Share July 12, 2024 on Facebook Share July 12, 2024 on X (formerly Twitter) Share July 12, 2024 on Linkedin Email July 12, 2024 link
    • Contractor anticipates starting Microseal work in August 2024.
    • Crack seal in Meridian complete.
    • RRFB at Meridian Rd & Bower ongoing.
    • Contractor anticipates starting Microseal work in August 2024.
    • Crack seal in Meridian complete.
    • RRFB at Meridian Rd & Bower ongoing.

    This project is substantially complete.

  • June 28, 2024

    Share June 28, 2024 on Facebook Share June 28, 2024 on X (formerly Twitter) Share June 28, 2024 on Linkedin Email June 28, 2024 link
    • Contractor anticipates starting Microseal work in August 2024.
    • Crack seal in Meridian complete.
    • RRFB at Meridian Rd & Bower ongoing.
    • Contractor anticipates starting Microseal work in August 2024.
    • Crack seal in Meridian complete.
    • RRFB at Meridian Rd & Bower ongoing.

    This project is substantially complete.

  • June 14, 2024

    Share June 14, 2024 on Facebook Share June 14, 2024 on X (formerly Twitter) Share June 14, 2024 on Linkedin Email June 14, 2024 link
    • Preconstruction meeting was held May 7th
    • Contractor anticipates starting microseal work in August 2024
    • Crack seal in Meridian complete
    • Preconstruction meeting was held May 7th
    • Contractor anticipates starting microseal work in August 2024
    • Crack seal in Meridian complete

    This project is substantially complete.

  • June 7, 2024

    Share June 7, 2024 on Facebook Share June 7, 2024 on X (formerly Twitter) Share June 7, 2024 on Linkedin Email June 7, 2024 link
    • Preconstruction meeting was held May 7th
    • Contractor anticipates starting microseal work in August 2024
    • Crack seal in Meridian started the week of May 28th and is on-going
    • Preconstruction meeting was held May 7th
    • Contractor anticipates starting microseal work in August 2024
    • Crack seal in Meridian started the week of May 28th and is on-going

    This project is substantially complete.