February 9, 2024

  • Road closed for the duration of the work.
  • Headwalls and concrete placed.
  • Backfilling structure.
  • Curb and gutter placement starting February 9th.
Share February 9, 2024 on Facebook Share February 9, 2024 on Twitter Share February 9, 2024 on Linkedin Email February 9, 2024 link

This project is substantially complete. 