January 12, 2024

  • Road closed for the duration of the work.
  • Lumen relocated utilities.
  • Contractor removing asphalt.
  • Placed culvert.
  • Setting forms for concrete
Share January 12, 2024 on Facebook Share January 12, 2024 on X (formerly Twitter) Share January 12, 2024 on Linkedin Email January 12, 2024 link

This project is substantially complete. 