April 19, 2024
- Sewer work for Garden City complete within project limits.
- Road base prep is complete.
- Asphalt paving was completed on April 18th.
Share April 19, 2024 on Facebook
Share April 19, 2024 on X (formerly Twitter)
Share April 19, 2024 on Linkedin
Email April 19, 2024 link
Work substantially complete.