April 19, 2024
- Sewer work for Garden City complete within project limits.
- Road base prep is complete.
- Asphalt paving was completed on April 18th.
Share April 19, 2024 on Facebook
Share April 19, 2024 on Twitter
Share April 19, 2024 on Linkedin
Email April 19, 2024 link
Work substantially complete.