December 15, 2023
- 37th Street will be closed for the duration of the work.
- Utility work continues. o Bridge/Culvert demo complete.
- Coordination with Garden City sewer work continues.
Share December 15, 2023 on Facebook
Share December 15, 2023 on X (formerly Twitter)
Share December 15, 2023 on Linkedin
Email December 15, 2023 link
Work substantially complete.