December 8, 2023

  • Utility work started November 15th.
  • Bridge/Culvert demo started.
  • Notification boards have been set.
  • 37th Street will be closed for the duration of the work.
  • Coordination with Garden City sewer work continues.
Share December 8, 2023 on Facebook Share December 8, 2023 on X (formerly Twitter) Share December 8, 2023 on Linkedin Email December 8, 2023 link

Work substantially complete. 