February 16, 2024

  • Sewer work for Garden City will start the first week of March.
  • Curb & gutter work complete.
  • Sidewalk placed this week.
Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link

Work substantially complete. 