January 5, 2024

  • Utility work ongoing.
  • Precast sections have been set.
  • Coordination with Garden City sewer work continues.
  • Wing walls and cast-in-place box have been placed.
Share January 5, 2024 on Facebook Share January 5, 2024 on X (formerly Twitter) Share January 5, 2024 on Linkedin Email January 5, 2024 link

Work substantially complete. 