April 21, 2023

  • Brandon Road and Floating Feather Roads are both closed.
  • Installing City of Star's sewer - complete.
  • All culverts are complete.
  • Floating Feather - asphalt removed; contractor placing base gravels.
Share April 21, 2023 on Facebook Share April 21, 2023 on Twitter Share April 21, 2023 on Linkedin Email April 21, 2023 link

This project is substantially complete.