April 7, 2023
- Brandon Road and Floating Feather Roads are both closed.
- Installing City of Star's sewer - ongoing.
- Foothill Ditch - complete.
- Lateral 12 culvert - complete.
- Water is flowing.
- Floating Feather - Box culvert - complete, backfill complete.
- Grade crew starting the week of April 10th - prepping for sidewalk and road.