April 7, 2023

  • Brandon Road and Floating Feather Roads are both closed.
  • Installing City of Star's sewer - ongoing.
  • Foothill Ditch - complete.
  • Lateral 12 culvert - complete.
  • Water is flowing.
  • Floating Feather - Box culvert - complete, backfill complete.
  • Grade crew starting the week of April 10th - prepping for sidewalk and road.
Share April 7, 2023 on Facebook Share April 7, 2023 on Twitter Share April 7, 2023 on Linkedin Email April 7, 2023 link

This project is substantially complete.