March 17, 2023
- Brandon Road and Floating Feather are both closed.
- Installing City of Star's sewer - ongoing.
- Foothill Ditch - complete.
- Lateral 12 - Box pieces set.
- Headwall placed March 15th.
- Floating Feather - Box pieces set. Closure pours ongoing. Headwalls ongoing. Placing waterproof membrane.