May 5, 2023
- Brandon Road and Floating Feather are both closed.
- Installing City of Star's sewer - complete.
- All culverts are complete.
- Floating Feather Road
- Asphalt removed - contractor placing base gravels.
- Paving anticipated May 12th
- Brandon Road
- Repairing soft spots and placing gravel