February 10, 2023
- Lena Bridge - ongoing. Concrete pad and backfill remaining.
- CIPP liner ongoing. Bike rail ongoing.
- Wildwood Bridge - demo starting on the 23rd. Pipe is placed. Backfilling road, waiting for hot plants to open.
- Bryson Bridge - Clearing and grubbing. Excavating for footers.