February 3, 2023

  • Lena Bridge is ongoing - concrete pad and backfill remaining.
  • CIPP liner ongoing. Bike rail ongoing.
  • Wildwood Bridge - Demo on bridge starting January 23rd.
  • Gas conflict anticipated being lowered starting February 1.
  • Bryson Bridge - Precast boxes completed by February 3rd.