February 3, 2023
- Lena Bridge is ongoing - concrete pad and backfill remaining.
- CIPP liner ongoing. Bike rail ongoing.
- Wildwood Bridge - Demo on bridge starting January 23rd.
- Gas conflict anticipated being lowered starting February 1.
- Bryson Bridge - Precast boxes completed by February 3rd.