- Culvert installed - Bryson Road.
- Headwalls placed - waiting for concrete strength before backfilling.
- Backfill walls starting the week of March 13th.
- Wildwood Bridge - Backfilling the road, waiting for hot plants to open. Finishing curb and sidewalk the week of March 6th.