July 12, 2024

  • Pipe and seepage bed complete.
  • Curb concrete complete.
  • Sidewalk concrete placement this week.
  • Paving and lane lines scheduled for late this week, or early next week.
Share July 12, 2024 on Facebook Share July 12, 2024 on Twitter Share July 12, 2024 on Linkedin Email July 12, 2024 link

This project is substantially complete. 