June 26, 2026
- Construction is complete on the north and south sides of Chinden.
- Traffic has been restored to its normal configuration.
- Concrete work is complete.
- A fog seal will be placed on Chinden the night of June 29th.
- Striping will be installed the night of June 30th.
- The pedestrian signal will be activated on the night of July 2nd.
Share June 26, 2026 on Facebook
Share June 26, 2026 on X (formerly Twitter)
Share June 26, 2026 on Linkedin
Email June 26, 2026 link
This project is substantially complete.