Columbia Road Bridge

Share Columbia Road Bridge on Facebook Share Columbia Road Bridge on Twitter Share Columbia Road Bridge on Linkedin Email Columbia Road Bridge link

This project is substantially complete. 

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the bridge on Columbia Road east of Ten Mile Road, as early as the beginning of October 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Kuna Canal.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the bridge on Columbia Road east of Ten Mile Road, as early as the beginning of October 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Kuna Canal.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

This project is substantially complete. 

  • April 25, 2024

    Share April 25, 2024 on Facebook Share April 25, 2024 on Twitter Share April 25, 2024 on Linkedin Email April 25, 2024 link

    This project is substantially complete.

  • April 12, 2024

    Share April 12, 2024 on Facebook Share April 12, 2024 on Twitter Share April 12, 2024 on Linkedin Email April 12, 2024 link
    • Columbia Road closed for the duration of the project.
    • Excavating road - Ongoing.
    • Paving anticipated April 10th.
    • Sand window ongoing.
  • April 5, 2024

    Share April 5, 2024 on Facebook Share April 5, 2024 on Twitter Share April 5, 2024 on Linkedin Email April 5, 2024 link
    • Columba Road closed for the duration of the project.
    • Excavating road - Ongoing.
    • Paving anticipated April 10th.
  • March 29, 2024

    Share March 29, 2024 on Facebook Share March 29, 2024 on Twitter Share March 29, 2024 on Linkedin Email March 29, 2024 link
    • Columba Road closed for the duration of the project.
    • Excavating road - Ongoing.
    • Paving anticipated April 10th.
  • March 21, 2024

    Share March 21, 2024 on Facebook Share March 21, 2024 on Twitter Share March 21, 2024 on Linkedin Email March 21, 2024 link
    • Columbia Road closed for the duration of the project.
    • Prepping for sidewalk.
    • Excavating road - Ongoing.
    • Placing Rip Rap.
  • March 15, 2024

    Share March 15, 2024 on Facebook Share March 15, 2024 on Twitter Share March 15, 2024 on Linkedin Email March 15, 2024 link
    • Columba Road closed for the duration of the project.
    • Prepping for sidewalk.
    • Excavating road. Ongoing.
    • Placing Rip Rap.
  • March 8, 2024

    Share March 8, 2024 on Facebook Share March 8, 2024 on Twitter Share March 8, 2024 on Linkedin Email March 8, 2024 link
    • Columba Road closed for the duration of the project.
    • Apron placed February 28th.
    • Excavating road.
  • March 1, 2024

    Share March 1, 2024 on Facebook Share March 1, 2024 on Twitter Share March 1, 2024 on Linkedin Email March 1, 2024 link
    • Columba Road closed for the duration of the project.
    • Apron being placed February 28th.
    • Excavating road.
  • February 23, 2024

    Share February 23, 2024 on Facebook Share February 23, 2024 on Twitter Share February 23, 2024 on Linkedin Email February 23, 2024 link
    • Columbia Road closed for the duration of the project.
    • Apron remaining.
    • Excavating road.
  • February 16, 2024

    Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link
    • Columba Road closed for the duration of the project.
    • Culvert placed.
    • Deck placed.
    • Forming headwalls.