This project is substantially complete.
-
Share October 12, 2023 on Facebook
Share October 12, 2023 on X (formerly Twitter)
Share October 12, 2023 on Linkedin
Email October 12, 2023 link
This project is substantially complete
This project is substantially complete
This project is substantially complete.
-
Share August 31, 2023 on Facebook
Share August 31, 2023 on X (formerly Twitter)
Share August 31, 2023 on Linkedin
Email August 31, 2023 link
- Concrete placements complete on Cory Lane.
- Work on Mitchell started August 16th - nearly complete.
- Minor concrete repair and asphalt patching remaining.
- Concrete placements complete on Cory Lane.
- Work on Mitchell started August 16th - nearly complete.
- Minor concrete repair and asphalt patching remaining.
This project is substantially complete.
-
Share August 25, 2023 on Facebook
Share August 25, 2023 on X (formerly Twitter)
Share August 25, 2023 on Linkedin
Email August 25, 2023 link
- Concrete placements complete on Cory Lane.
- Work on Mitchell started August 16th - nearly complete.
- Concrete placements complete on Cory Lane.
- Work on Mitchell started August 16th - nearly complete.
This project is substantially complete.
-
Share August 18, 2023 on Facebook
Share August 18, 2023 on X (formerly Twitter)
Share August 18, 2023 on Linkedin
Email August 18, 2023 link
- Concrete placements complete on Cory Lane.
- Work on Mitchell started August 16th.
- Concrete placements complete on Cory Lane.
- Work on Mitchell started August 16th.
This project is substantially complete.
-
Share August 4, 2023 on Facebook
Share August 4, 2023 on X (formerly Twitter)
Share August 4, 2023 on Linkedin
Email August 4, 2023 link
- Work continues on north side of Cory.
- Concrete prep and placements are nearly complete.
- Paving complete.
- Work continues on north side of Cory.
- Concrete prep and placements are nearly complete.
- Paving complete.
This project is substantially complete.
-
Share July 28, 2023 on Facebook
Share July 28, 2023 on X (formerly Twitter)
Share July 28, 2023 on Linkedin
Email July 28, 2023 link
- Work continues on the north side of Cory.
- One way traffic set for vehicles to travel east only, between Maple Grove and Mitchell.
- Concrete prep and placements ongoing.
- Target pave date for end of July.
- Work continues on the north side of Cory.
- One way traffic set for vehicles to travel east only, between Maple Grove and Mitchell.
- Concrete prep and placements ongoing.
- Target pave date for end of July.
This project is substantially complete.
-
Share July 14, 2023 on Facebook
Share July 14, 2023 on X (formerly Twitter)
Share July 14, 2023 on Linkedin
Email July 14, 2023 link
- Work continues on the north side of Cory
- One-way traffic set for vehicles to travel east only, between Maple Grove and Mitchell
- Concrete prep and placements ongoing
- Target pave date for end of July
- Work continues on the north side of Cory
- One-way traffic set for vehicles to travel east only, between Maple Grove and Mitchell
- Concrete prep and placements ongoing
- Target pave date for end of July
This project is substantially complete.
-
Share July 7, 2023 on Facebook
Share July 7, 2023 on X (formerly Twitter)
Share July 7, 2023 on Linkedin
Email July 7, 2023 link
- Work continues on the north side of Cory.
- One-way traffic set for vehicles to travel east only, between Maple Grove and Mitchell.
- Utility work nearly complete on the north side of the road.
- Concrete prep and placements ongoing.
- Work continues on the north side of Cory.
- One-way traffic set for vehicles to travel east only, between Maple Grove and Mitchell.
- Utility work nearly complete on the north side of the road.
- Concrete prep and placements ongoing.
This project is substantially complete.
-
Share June 30, 2023 on Facebook
Share June 30, 2023 on X (formerly Twitter)
Share June 30, 2023 on Linkedin
Email June 30, 2023 link
- Work continues on the north side of Cory.
- One-way traffic set for vehicles to travel east only, between Maple Grove and Mitchell.
- Utility work nearly complete on north side of road.
- Concrete prep and placements ongoing.
- Work continues on the north side of Cory.
- One-way traffic set for vehicles to travel east only, between Maple Grove and Mitchell.
- Utility work nearly complete on north side of road.
- Concrete prep and placements ongoing.
This project is substantially complete.
-
Share June 23, 2023 on Facebook
Share June 23, 2023 on X (formerly Twitter)
Share June 23, 2023 on Linkedin
Email June 23, 2023 link
- Work continues on the north side of Cory.
- One-way traffic set for vehicles to travel east only, between Maple Grove and Mitchell.
- Utility work ongoing on north side of the road.
- Concrete prep and placements ongoing.
- Work continues on the north side of Cory.
- One-way traffic set for vehicles to travel east only, between Maple Grove and Mitchell.
- Utility work ongoing on north side of the road.
- Concrete prep and placements ongoing.
This project is substantially complete.