Deep Canyon Avenue Pavement Maintenance

Share Deep Canyon Avenue Pavement Maintenance on Facebook Share Deep Canyon Avenue Pavement Maintenance on X (formerly Twitter) Share Deep Canyon Avenue Pavement Maintenance on Linkedin Email Deep Canyon Avenue Pavement Maintenance link

This project is substantially complete. 

Starting as early as June 2026, Ada County Highway District will begin road maintenance work on Deep Canyon Avenue, from Highway 16 to High Country Way, as part of the 2027 Arterial & Collector Capital Maintenance project.

Construction is anticipated to be complete by late summer 2026.*

Why is this work needed?

The pavement along Deep Canyon Avenue is in poor condition and needs maintenance. This project will rehabilitate the roadway pavement to help preserve the roadway and provide a smoother, safer driving surface.

What to expect during construction

Residents should expect temporary impacts, including:

  • Lane restrictions with flaggers
  • On-street parking restrictions
  • General construction noise, dust, equipment backup alarms, and ground vibration

Crews will typically work from 7 a.m. to 7 p.m., unless otherwise approved.

The contractor will work with property owners to minimize impacts. Access to homes will be maintained as much as possible. Trash collection, mail delivery, and emergency access will be maintained throughout construction.


*Construction schedules may change.

Starting as early as June 2026, Ada County Highway District will begin road maintenance work on Deep Canyon Avenue, from Highway 16 to High Country Way, as part of the 2027 Arterial & Collector Capital Maintenance project.

Construction is anticipated to be complete by late summer 2026.*

Why is this work needed?

The pavement along Deep Canyon Avenue is in poor condition and needs maintenance. This project will rehabilitate the roadway pavement to help preserve the roadway and provide a smoother, safer driving surface.

What to expect during construction

Residents should expect temporary impacts, including:

  • Lane restrictions with flaggers
  • On-street parking restrictions
  • General construction noise, dust, equipment backup alarms, and ground vibration

Crews will typically work from 7 a.m. to 7 p.m., unless otherwise approved.

The contractor will work with property owners to minimize impacts. Access to homes will be maintained as much as possible. Trash collection, mail delivery, and emergency access will be maintained throughout construction.


*Construction schedules may change.

This project is substantially complete. 

  • July 1, 2026

    Share July 1, 2026 on Facebook Share July 1, 2026 on X (formerly Twitter) Share July 1, 2026 on Linkedin Email July 1, 2026 link
    • Mainline paving and approaches are complete.
    • Landscape repair will be ongoing for the next week or two.
    • Mainline paving and approaches are complete.
    • Landscape repair will be ongoing for the next week or two.

    This project is substantially complete. 

  • June 26, 2026

    Share June 26, 2026 on Facebook Share June 26, 2026 on X (formerly Twitter) Share June 26, 2026 on Linkedin Email June 26, 2026 link
    • Contractor has started to mill the existing roadway.
    • Paving is scheduled for next week, pending weather.
    • Contractor has started to mill the existing roadway.
    • Paving is scheduled for next week, pending weather.

    This project is substantially complete. 

  • June 18, 2026

    Share June 18, 2026 on Facebook Share June 18, 2026 on X (formerly Twitter) Share June 18, 2026 on Linkedin Email June 18, 2026 link
    • Work is anticipated to start on June 24th.
    • Deep Canyon Drive will be closed with local access allowed.
    • Work is anticipated to start on June 24th.
    • Deep Canyon Drive will be closed with local access allowed.

    This project is substantially complete. 

  • June 5, 2026

    Share June 5, 2026 on Facebook Share June 5, 2026 on X (formerly Twitter) Share June 5, 2026 on Linkedin Email June 5, 2026 link
    • Work is anticipated to start in June.
    • Work is anticipated to start in June.

    This project is substantially complete.