Eckert Road Bridge
The Eckert Road Bridge is back open to vehicles, pedestrians and bicyclists after the completion of interim repairs. A final inspection by the Idaho Transportation Department confirmed that the bridge is safe for passenger vehicles and commercial traffic within legal load limits.
The bridge was closed in January 2025 after an inspection identified significant structural decay. ACHD and ITD collaborated to complete the repairs quickly and safely, and reopened the bridge March 10.
ACHD is actively working on plans for a full reconstruction of the bridge, with design work already underway. Construction is tentatively scheduled to begin in fall 2026. Updates on the replacement project will be provided as planning progresses.
The Eckert Road Bridge is back open to vehicles, pedestrians and bicyclists after the completion of interim repairs. A final inspection by the Idaho Transportation Department confirmed that the bridge is safe for passenger vehicles and commercial traffic within legal load limits.
The bridge was closed in January 2025 after an inspection identified significant structural decay. ACHD and ITD collaborated to complete the repairs quickly and safely, and reopened the bridge March 10.
ACHD is actively working on plans for a full reconstruction of the bridge, with design work already underway. Construction is tentatively scheduled to begin in fall 2026. Updates on the replacement project will be provided as planning progresses.
-
ACHD, ITD Complete Interim Repairs on Eckert Bridge; Bridge to Reopen Today
Share ACHD, ITD Complete Interim Repairs on Eckert Bridge; Bridge to Reopen Today on Facebook Share ACHD, ITD Complete Interim Repairs on Eckert Bridge; Bridge to Reopen Today on Twitter Share ACHD, ITD Complete Interim Repairs on Eckert Bridge; Bridge to Reopen Today on Linkedin Email ACHD, ITD Complete Interim Repairs on Eckert Bridge; Bridge to Reopen Today link10 Mar 2025BOISE — Interim repairs on the Eckert Road Bridge are now complete, and the structure is once again safe for travel. Following a final inspection, the Idaho Transportation Department (ITD) has confirmed that the bridge can reopen for passenger vehicles and commercial traffic that meet legal load requirements. The bridge is scheduled to reopen by the end of the day today, Monday, March 10.
The bridge was originally closed at the end of January after a routine inspection revealed severe decay in its support structures. Given the urgency of the situation, ITD developed a repair plan based off of a similar bridge in northern Idaho and worked in tandem with ACHD to secure emergency permits from the U.S. Army Corps of Engineers.
“Public safety is always our top priority,” said Ryan Head, ACHD Director. “This project was a true testament to the power of partnership. We appreciate ITD’s quick response in developing a repair plan, and we thank the public for their patience as we worked to ensure the bridge’s safety. This collaboration allowed us to address a critical issue and restore access as quickly as possible.”
Repairs began on February 17, when crews started diverting a portion of the Boise River. The repair process involved using steel plate channels to reinforce the bridge’s support piles, with each pile then supported by a concrete base. Crews worked in phases, diverting one half of the river at a time. Crews from ACHD and ITD worked together each day, including over weekends and holidays, to complete the repairs as quickly as possible.
“This project required a rapid and coordinated effort, and we’re pleased with the outcome,” said ITD Chief Deputy Director Dan McElhinney. “Our teams worked tirelessly to ensure the bridge could safely reopen before river levels rose, and we’re grateful for the collaboration that made it possible.”
After crews finished repairs on all severely decayed piles, along with several that showed moderate decay, ITD conducted a final inspection to ensure the bridge was safe to reopen with no weight restriction. The repairs were completed in time for the summer float season, ensuring safe access for vehicles, bicycles, and pedestrians.
ACHD and ITD completed the project in a joint effort, with ACHD reimbursing ITD for materials and staff time. While final accounting of costs is still being completed, the estimated cost of the interim repairs is $500,000.
ACHD remains committed to the long-term reconstruction of the Eckert Bridge, with accelerated design work having begun in early February. The District is tentatively aiming to begin reconstruction on the bridge in fall 2026. More details on the full replacement project will be shared as plans progress.
-
Repair Update- February 28th
Share Repair Update- February 28th on Facebook Share Repair Update- February 28th on Twitter Share Repair Update- February 28th on Linkedin Email Repair Update- February 28th link01 Feb 2025Crews have been working daily, including weekends, since interim repairs began on Monday, February 17th. Crews have diverted half of the Boise River at a time to conduct the repair work.Earlier this week, crews finished repair work on all piles that showed severe decay on the northern side of the bridge. They then shifted operations to divert the southern half of the river and began addressing severely decayed piles on the southern side.
By the end of the day tomorrow (Saturday), repairs on all bridge piles that were determined to have severe decay are expected to be complete.
Starting Monday, crews will begin work on piles that have shown moderate decay, beginning on the southern side of the bridge. ACHD will continue coordinating with ITD to inspect the bridge and determine when it is safe to reopen.
-
Live from Eckert Bridge
Share Live from Eckert Bridge on Facebook Share Live from Eckert Bridge on Twitter Share Live from Eckert Bridge on Linkedin Email Live from Eckert Bridge link26 Feb 2025Senior Public Information Officer Rachel Bjornestad talks all things Eckert Bridge with Tom Otte, ACHD's Deputy Director of Operations.
-
Interim Repair Work is Underway
Share Interim Repair Work is Underway on Facebook Share Interim Repair Work is Underway on Twitter Share Interim Repair Work is Underway on Linkedin Email Interim Repair Work is Underway link25 Feb 2025Crews are making progress on interim repairs to the Eckert Road Bridge. ACHD and ITD crews are working as the weather allows.
Piles on pier six and pier seven have been bolted, and concrete has been poured. Work on the northern side of the bridge is nearing completion. Once work on the northern side is complete, crews will move to the south side of the bridge.
The bridge is closed to bicyclists and pedestrians, as well as vehicles. The bicycle and pedestrian bridge is also closed for the duration of the repair work.
We understand detours can be inconvenient, but for the safety of all commuters and staff working on the bridge, please do not use the bridge at this time.
While the bridge is closed, bicyclists and pedestrians should use the East Parkcenter Bridge (see detour map).
As a reminder, access to Barber Park is still open directly south of the bridge.
-
ACHD and ITD Begin Work on Interim Repairs for Eckert Road Bridge in Boise
Share ACHD and ITD Begin Work on Interim Repairs for Eckert Road Bridge in Boise on Facebook Share ACHD and ITD Begin Work on Interim Repairs for Eckert Road Bridge in Boise on Twitter Share ACHD and ITD Begin Work on Interim Repairs for Eckert Road Bridge in Boise on Linkedin Email ACHD and ITD Begin Work on Interim Repairs for Eckert Road Bridge in Boise link15 Feb 2025BOISE — The Ada County Highway District (ACHD) and the Idaho Transportation Department (ITD) are pleased to announce that work is beginning on interim repairs for the Eckert Road Bridge, which was built over the Boise River in 1954. This collaborative effort aims to allow the bridge to temporarily reopen by the end of spring, providing additional time for the design and planning of a long-term replacement.
Since the emergency bridge closure, staff at ITD have been working diligently on a plan for interim repairs following ACHD’s decision to close the bridge at the end of January. ITD designed the repair plan based on prior work on a similar bridge in northern Idaho, and bridge engineers have confirmed that it is suitable for the Eckert Road Bridge. Additionally, ITD has procured the needed materials for the project and worked in coordination with ACHD to secure emergency permits from the U.S. Army Corps of Engineers.
Now with the design complete and permits in hand, ACHD and ITD crews plan to begin work in the river next week. Work is expected to begin as early as Monday, February 17. During the repair work, the pedestrian and bicycle bridge will be closed for safety. The main bridge will also be closed to bicycles and pedestrians.
The interim repairs are estimated to take four to eight weeks to complete. However, the exact timeline of repairs will depend on how long it takes each pile to be reinforced, as well as the available window for crews to work in the river before spring flows rise. ACHD expects to have a more accurate time frame as the work progresses.
The repair process will involve using steel plate channels to reinforce the bridge’s support piles. Specifically, two plates will be bolted together around each affected timber pile and then supported by a concrete base.
Working in the river poses unique challenges. To install concrete bases for the steel reinforcements, ACHD will need to divert a portion of the river. Work will end in time for spring runoff, at which point water levels will be too high to continue safely working.
“ITD has been a critical partner in ensuring we can get this bridge reopened as quickly and safely as possible,” ACHD Director Ryan Head said. “We appreciate our partner agency’s expertise and assistance in developing and executing this interim repair plan. These repairs aim to allow for the reopening prior to our popular float season while also providing ACHD additional time to properly plan for a long-term replacement.”
ACHD and ITD will complete the work in a joint effort, with ACHD reimbursing ITD for materials and staff time. The estimated cost to repair the bridge is $500,000. Crews will divert half of the Boise River at a time in this area to complete the repairs.
“ITD is bringing its expertise to help expedite this emergency bridge repair,” ITD Chief Deputy Director Dan McElhinney said. “This teamwork demonstrates the strength of interagency collaboration, and we are committed to reopening for the community and emergency services to have a safe and functional crossing while the long-term replacement project solutions are developed.”
-
Investing in Idaho’s Future: A Thank You to Our State Leaders
Share Investing in Idaho’s Future: A Thank You to Our State Leaders on Facebook Share Investing in Idaho’s Future: A Thank You to Our State Leaders on Twitter Share Investing in Idaho’s Future: A Thank You to Our State Leaders on Linkedin Email Investing in Idaho’s Future: A Thank You to Our State Leaders link09 Feb 2025As members of the Ada County Highway District (ACHD) Board of Commissioners, we extend our deepest gratitude to Governor Brad Little, the Idaho Legislature, and the leaders behind the Leading Idaho Local Bridge Program. Your commitment to investing in Idaho’s aging infrastructure through the Local Highway Technical Assistance Council (LHTAC) is a testament to your vision, leadership, and unwavering dedication to the communities we serve.
A prime example of the impact of this initiative is the funding provided for the reconstruction of the Eckert Road Bridge—an essential connection for residents, businesses, and emergency responders in Ada County. Originally scheduled for replacement in the coming years, recent inspections revealed rapid deterioration, making an accelerated reconstruction imperative. Thanks to the funding made available through the Leading Idaho Local Bridge Program, we can expedite the replacement of this critical bridge while minimizing disruptions to other essential infrastructure projects throughout the county.
The significance of this investment cannot be overstated. Infrastructure is the backbone of our communities, facilitating economic growth, safety, and connectivity. By prioritizing the replacement and improvement of Idaho’s bridges, our state leaders have demonstrated a deep understanding of the long-term needs of a growing population. Their foresight ensures that our bridges remain safe and functional, supporting Idahoans today and for generations to come.
This proactive approach to infrastructure funding is a model of responsible governance—one that acknowledges the importance of maintaining and enhancing critical the transportation network, ultimately protecting the safety of the public. The ability to address essential bridge repairs and replacements in hundreds of communities large and small, reflects the wisdom and responsiveness of Idaho’s leadership.
On behalf of ACHD and the residents we serve, we thank you for your continued support, partnership and commitment to strengthening Idaho’s transportation system. The Leading Idaho Local Bridge Program is not just an investment in infrastructure—it is an investment in the future of our communities, our economy, and our shared prosperity.
ACHD Board of Commissioners
-
Friday, February 7th Update
Share Friday, February 7th Update on Facebook Share Friday, February 7th Update on Twitter Share Friday, February 7th Update on Linkedin Email Friday, February 7th Update link07 Feb 2025Eckert Bridge – February 7 Update
We are pleased to share that the Local Highway Technical Assistance Council (LHTAC) has voted to accept and fund ACHD’s application for the Eckert Road Bridge replacement under the Leading Idaho Local Bridge Program. This means that both the design and construction costs for the new bridge will be covered by state funds set aside specifically for projects like this. ACHD will work closely with LHTAC as they administer the contract to ensure this critical project moves forward efficiently.
At this time, we are still working to determine the exact dollar amount of funding that qualifies for the project. Additionally, we do not yet have a finalized timeline for reconstruction, but we will provide updates as soon as more details are available.
ITD and ACHD are also looking into potential interim solutions that could reinforce the bridge while planning for its replacement. ACHD staff will fully explore its feasibility and potential impacts. More information on this will be shared next week.Finally, we want to remind the public that Barber Park remains accessible. The entrance to the park is open, and we have provided an updated map to show the location of access into the park.ACHD appreciates the patience and support of the public as we work through the next steps. More updates will be provided as information becomes available. Please continue to check this page for the latest developments. -
Press Conference
Share Press Conference on Facebook Share Press Conference on Twitter Share Press Conference on Linkedin Email Press Conference link01 Jan 2025January 31, 2025 - 3PM
-
Press Release
Share Press Release on Facebook Share Press Release on Twitter Share Press Release on Linkedin Email Press Release link01 Jan 2025January 31, 2025 | 2:30PM
ACHD has announced the immediate closure of the Eckert Road Bridge following findings from a recent inspection that revealed widespread structural decay.
A press conference will be held today, Friday, January 31, at 3 p.m. in the auditorium at ACHD headquarters (3775 N Adams St) in Garden City to discuss the situation with media. Members of the media who would like to participate must RSVP to communications@achdidaho.org.
Following findings from an inspection report, ACHD was informed of significant deterioration affecting the bridge's load capacity. Specifically, the consultant’s assessment found moderate to severe decay on 22 out of the 48 bridge pillars. Additionally, on the center pier, five out of six timber piles exhibited severe decay.
Based on these findings, the Idaho Transportation Department recommended an immediate weight restriction of three tons. In the interest of public safety, ACHD has opted to close the bridge to all motor vehicle traffic, effective immediately. The bridge will remain open to bicycle and pedestrian traffic.
This morning, the ACHD Commission held a special meeting to approve the bridge closure. A link to the meeting is available on ACHD’s website for public access.
ACHD installed road closure signs along the bridge today, and will install advanced warning signage to help commuters navigate alternate routes.
The duration of the closure remains uncertain. ACHD will provide more information to the public on the timeline as it becomes available.
For further updates and detour information, please visit achdidaho.org/eckertbridge.
STREAMING INFORMATION: The meeting will be livestreamed and can be accessed at achdidaho.org/live(External link) for those who wish to watch virtually. The meeting will also be posted on ACHD's website and YouTube. -
Commission - Special Meeting
Share Commission - Special Meeting on Facebook Share Commission - Special Meeting on Twitter Share Commission - Special Meeting on Linkedin Email Commission - Special Meeting link01 Jan 2025January 31, 2025 - 11:30am
Logo
Follow Project
Documents
-
ITD Re-open letter (13.3 MB) (pdf)
-
ITD Critical Findings Notification (190 KB) (pdf)
-
Eckert Road Feasibility Study - Field Condition Assessment January 2025.pdf (32.6 MB) (pdf)
-
October 2022 Inspection by ITD Consultant (1.78 MB) (pdf)
-
October 2020 Inspection by ITD Consultant - Resistivity Testing (1.74 MB) (pdf)
-
November 2019 Inspection by ACHD Consultant - Resistivity Testing (5.69 MB) (pdf)
-
Adopted Resolution (1.48 MB) (pdf)
-
Letter of Support_City of Boise (577 KB) (pdf)
Important Links
Who's Listening
-
Sr. Project Manager
Phone 208-387-6100 Email projects@achdidaho.org (External link)