Fiddler Drive Bridge

Share Fiddler Drive Bridge on Facebook Share Fiddler Drive Bridge on Twitter Share Fiddler Drive Bridge on Linkedin Email Fiddler Drive Bridge link

This project is substantially complete.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Fiddler Drive west of Arlen Drive, as early as the beginning of October 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Zinger Lateral.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Fiddler Drive west of Arlen Drive, as early as the beginning of October 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Zinger Lateral.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

This project is substantially complete.

  • April 25, 2024

    Share April 25, 2024 on Facebook Share April 25, 2024 on Twitter Share April 25, 2024 on Linkedin Email April 25, 2024 link

    This project is substantially complete.

    This project is substantially complete.

    This project is substantially complete.

  • March 21, 2024

    Share March 21, 2024 on Facebook Share March 21, 2024 on Twitter Share March 21, 2024 on Linkedin Email March 21, 2024 link
    • Paving scheduled for March 14th.
    • Utility companies patching their work.
    • Paving scheduled for March 14th.
    • Utility companies patching their work.

    This project is substantially complete.

  • March 15, 2024

    Share March 15, 2024 on Facebook Share March 15, 2024 on Twitter Share March 15, 2024 on Linkedin Email March 15, 2024 link
    • Paving scheduled for March 14th.
    • Paving scheduled for March 14th.

    This project is substantially complete.

  • March 8, 2024

    Share March 8, 2024 on Facebook Share March 8, 2024 on Twitter Share March 8, 2024 on Linkedin Email March 8, 2024 link
    • Paving afterwards.
    • Excavating road.
    • Curb and gutter ongoing.
    • Paving afterwards.
    • Excavating road.
    • Curb and gutter ongoing.

    This project is substantially complete.

  • March 1, 2024

    Share March 1, 2024 on Facebook Share March 1, 2024 on Twitter Share March 1, 2024 on Linkedin Email March 1, 2024 link
    • Concrete headwalls remaining.
    • Sidewalk and curb remaining.
    • Paving afterwards.
    • Concrete headwalls remaining.
    • Sidewalk and curb remaining.
    • Paving afterwards.

    This project is substantially complete.

  • February 23, 2024

    Share February 23, 2024 on Facebook Share February 23, 2024 on Twitter Share February 23, 2024 on Linkedin Email February 23, 2024 link
    • Concrete headwalls remaining.
    • Sidewalk and curb remaining.
    • Paving afterwards.
    • Concrete headwalls remaining.
    • Sidewalk and curb remaining.
    • Paving afterwards.

    This project is substantially complete.

  • February 16, 2024

    Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link
    • Culvert set.
    • Forming headwalls.
    • Sidewalk and curb ongoing.
    • Culvert set.
    • Forming headwalls.
    • Sidewalk and curb ongoing.

    This project is substantially complete.

  • February 9, 2024

    Share February 9, 2024 on Facebook Share February 9, 2024 on Twitter Share February 9, 2024 on Linkedin Email February 9, 2024 link
    • Road closed for the duration of the work.
    • Lumen relocating lines.
    • Mtn Companies excavating.
    • Culvert set.
    • Forming headwalls.
    • Road closed for the duration of the work.
    • Lumen relocating lines.
    • Mtn Companies excavating.
    • Culvert set.
    • Forming headwalls.

    This project is substantially complete.

  • February 2, 2024

    Share February 2, 2024 on Facebook Share February 2, 2024 on Twitter Share February 2, 2024 on Linkedin Email February 2, 2024 link
    • Road closed for the duration of the work.
    • Lumen relocating lines.
    • Mountain Companies is excavating.
    • Veolia relocating.
    • Road closed for the duration of the work.
    • Lumen relocating lines.
    • Mountain Companies is excavating.
    • Veolia relocating.

    This project is substantially complete.

  • January 26, 2024

    Share January 26, 2024 on Facebook Share January 26, 2024 on Twitter Share January 26, 2024 on Linkedin Email January 26, 2024 link
    • Road closed for the duration of the work.
    • Lumen relocating lines.
    • Veolia relocating lines - Ongoing.
    • Road closed for the duration of the work.
    • Lumen relocating lines.
    • Veolia relocating lines - Ongoing.

    This project is substantially complete.