  • Veolia utility work Bethel to Alpine: Main line being placed. Boring work started at Alpine.
  • Albion to Franklin - Installing irrigation lines and storm drain. Contractor excavating road. Prepping for curb and sidewalk.
  • Emerald to Bethel - Irrigation work ongoing.
  • Franklin Intersection - Irrigation complete.
Share April 12, 2024 on Facebook Share April 12, 2024 on Twitter Share April 12, 2024 on Linkedin Email April 12, 2024 link

This project is substantially complete.