April 25, 2024

  • Veolia utility work - Main line being placed.
  • Boring completed.
  • Working between Bethel and Emerald.
  • Albion to Franklin - Contractor excavating road. Prepping for curb and sidewalk. Curb anticipated being placed April 25th.
  • Emerald to Bethel - Irrigation work ongoing. Storm drain work ongoing.
  • Franklin Intersection - Irrigation Complete. PHB signal work started.
Share April 25, 2024 on Facebook Share April 25, 2024 on Twitter Share April 25, 2024 on Linkedin Email April 25, 2024 link

This project is substantially complete.