April 5, 2024
- Veolia utility work Bethel to Alpine - Main line being placed. Boring delayed pending railroad approval.
- Albion to Franklin - Installing irrigation lines and storm drain.
- Contractor excavating road.
- Prepping for curb and sidewalk.
- Emerald to Bethel - Irrigation work ongoing.
- Franklin Intersection - Irrigation Complete.
Share April 5, 2024 on Facebook
Share April 5, 2024 on Twitter
Share April 5, 2024 on Linkedin
Email April 5, 2024 link
This project is substantially complete.